Proposed centre: 139 places from 6 weeks to 5 years.
Land size: 2,970sqm
Proposed Building: Centre to be constructed in two portions, the northern portion being two-storey and the southern section single level.
Current status: Planning application approved through VCAT, July 2020. Currently in construction.
Planned Completion date: Early 2023.
Proposed centre: 122 places from 6 weeks to 5 years.
Land size: 2,868sqm
Proposed Building: Single level childcare centre.
Current status: Planning permit obtained, construction drawings complete. Project to be tendered.
Planned Completion date: Late 2023.
Proposed centre: 116 places from 6 weeks to 5 years.
Land size: 2,610sqm
Proposed Building: New single level childcare centre.
Current status: In construction.
Planned Completion date: Early 2023.
Proposed centre: 131 places from 6 weeks to 5 years.
Land size: 2,023sqm
Proposed Building: New two level childcare centre.
Current status: Town planning drawings complete, with council under a permit application.
Planned Completion date: Mid 2023.
Proposed centre: 108 places from 6 weeks to 5 years.
Land size: 1,402sqm
Proposed Building: New two level childcare centre with parking at grade.
Current status: Planning permit received, construction drawings nearing completion.
Planned Completion date: Mid 2023.